Housings, stubs, adapters, bushings and related internals used on gas-equipment prints often contain a bore, a stepped passage, a cross-hole or an intersection of drillings. Those internal features are component characteristics. They are produced and inspected to the current revision. A diameter that is inside tolerance is not a flow rating, a capacity, or a type test of a complete regulator, filter, slam-shut valve or station, and SUNHY does not quote those complete devices. The work stays on the part, in the same scope as other gas-equipment component parts.
What has to be visible on the revision
A complete call-out names each diameter or passage, its tolerance, its depth or length, and any step, chamfer, radius or thread that interrupts it. If two drillings intersect, the intersection condition — a sharp edge, a defined break, a maximum burr, or a blended radius — should be stated. “Bore to suit flow” or “passage as usual” is not complete. A type code, including any SH- example used only as an illustration, does not replace the internal views.
Related features should be consistent with the bore. A sealing face, an O-ring groove or a thread at the end of a passage is a separate characteristic and is taken from the same revision, as in the notes on sealing faces and on O-ring grooves and seal glands. Concentricity or runout between a bore and a thread or a seat is included when the print states it; see the note on concentricity of threads and seats.
Intersections, burrs and hidden edges
Cross-holes and intersecting drillings create edges that are not always visible from the end of the part. If the print limits burrs, requires a break, or prohibits a reduction of the passage at the intersection, that condition is part of the inspection plan. Deburring “as much as possible” is not a substitute for a stated edge condition, and a passage must not be opened beyond its tolerance in order to remove a burr. The method — brushing, a defined tool, abrasive flow, or another agreed process — is part of the route when it is needed to meet the print, and a change of that method is a process change.
Steps and undercuts inside the bore are measured from the stated origin. A depth taken from the wrong face, or a gauge that cannot reach the step, will not represent the characteristic. If a special gauge or a layout section is already required, it should be named in the enquiry.
What is not being offered
No Cv, no flow curve, and no “suitable for X m³/h” figure is offered for a complete device on the basis of a component bore. If the customer uses the diameter in a design calculation, that calculation remains the customer’s. A tightness or pressure check on the component, when it is specified, is still a test of the part, not a type test of a regulator or a station. Related scope language for internals is also used in the note on slam-shut valve internals sourced as components.
Material, finish and cleanliness
The material and any internal finish, including a coating or a cleanliness requirement in the passage, stay with the print, as in the note on materials and finishes on gas-equipment prints. A coating that reduces the bore, or a residue from washing, is reviewed against the diameter and the cleanliness note. Certificates and any EN 10204 3.1 evidence are confirmed per order when required.
Route and first article
Drilling, boring, reaming, turning and any secondary finishing of the passage follow the agreed route. A prototype that was spark-eroded or hand-finished does not by itself approve a later production drilling route if the intersection or the surface will change. First-article inspection, when required, should include the internal characteristics that the print controls, as in the note on first-article inspection.
Measurement access, conflicts and volume
Some passages are too small, too deep, or too interrupted for a standard plug gauge to represent the whole characteristic. If a pin, an air gauge, a sectioned layout, or another method is already required, it should be named in the enquiry so that it can be planned. A gauge that only checks the mouth of the bore is not evidence of a deep step unless that is the agreed method. First-article inspection, when required, should say which internal features were measured and how.
A print that names a diameter and an intersection radius the tool cannot produce together, or that shows two crossing holes without an edge condition, is flagged. Mixed units or a title-block note that conflicts with a detailed bore are reviewed together. Volume belongs in the enquiry, because a prototype that was bored in a single setup may not represent a later gun-drilled or secondary-drilled passage. Those differences are stated in the quotation and are not changed after samples have been approved without a review. Packing that keeps chips or oil out of a finished passage is included when the order or the cleanliness note requires it.
What to send with the RFQ
Send the current drawing revision with complete internal views and tolerances, together with the material, finish and volume. If a particular gauge, a section, a cleanliness specification or a component tightness check is already required, say so. Unspecified points will be flagged before production rather than assumed.
This article is a capability and commercial note. It is not a certificate, a dimensional data book, or evidence of customer approval. Catalogue type codes and example grades do not replace the customer’s item number, material specification or drawing revision.