First-article inspection on a made-to-print part is a defined activity, included when the order requires it. It is not a free extra on every new item, and it is not the same thing as sending a few prototype pieces. The scope — which characteristics are measured, against which revision, with which method, and in which process condition — has to be agreed. A photograph of a part on a bench is not a first-article report.
SUNHY can include a first-article, ISIR or layout inspection for fasteners and for gas-equipment components when that work is specified. The legal name and the exact format follow the customer’s instruction. Documents of this kind are confirmed per order, in the same sense as the items in the note on EN 10204 3.1, inspection records, PPAP and IMDS.
What a first article is for
A first-article or layout report shows that a defined set of characteristics, measured on identified parts from a stated process, meet the current drawing revision. It is most useful when the series-intent route, the material, the heat treatment and the coating are already the ones that will be used in production, or when any difference is written down and accepted. Measuring a soft, uncoated, fully machined sample and treating the result as approval of a headed, heat-treated and coated series part is a category error.
That distinction is the same one drawn in the note on prototype samples and series production. If the first article will be taken from a temporary route, the report should say so, and a further layout from the production-intent route should be planned if the customer requires it.
Scope, ballooned drawings and methods
The enquiry should say whether every ballooned characteristic is to be reported, whether a subset is enough, and whether related notes — thread class, coating thickness, hardness, material — are part of the same submission. A ballooned drawing, a marked-up print, or a customer form helps. If only a dimensional layout is required, or if material and coating evidence are to be attached, state that split.
Methods follow the characteristic: go / no-go gauges, measured values, hardness, coating thickness, or a specified laboratory method. If a particular gauge, a CMM layout, or a thread method is already decided, name it. Where the print already sets the gauging condition of a thread, including after coating, the first-article method has to respect that condition — see thread standards, pitch and gauging.
Revision, identity and the parts that are measured
The report has to be tied to a drawing revision, an item number and the identity of the parts that were measured. If the revision changes after the first article, the status of that report is an open point: it may still cover unchanged characteristics, or a delta or a full re-layout may be required. That decision is the customer’s, and it should be written. The companion note on drawing revision control covers the commercial side of a revision change.
Lot identity, material certificates and, where specified, heat-treatment or coating records are linked to the same parts when the order requires that linkage. They are not assembled after the fact from a different lot.
What first-article inspection is not
A completed first-article report is not, by itself, PPAP approval, a capacity commitment, or approval of a later change of route, die, coating source or material grade. Those are separate decisions. Process-capability figures, if they are required at all, are a different request and are discussed in the note on process capability on drawing-controlled characteristics.
Quality-system certificates are not a substitute for a first-article report, and they are not presented as product approval. ISO 9001 may be referenced as a quality-system framework; the legal entity, site, scope and validity are confirmed for the order before any certificate is cited, as already stated on the quality page.
How many parts, who measures them, and the format of the report
The number of parts in a first-article submission, and whether they are consecutive, random, or taken from a stated position in the lot, should follow the customer’s standard or a written agreement. “A few pieces for checking” is not a sample plan. If the customer measures a duplicate set, or if a third-party laboratory is to be used for a named test, that split should be visible in the RFQ so that the remaining work, and the documents that travel with the parts, can be confirmed.
The format of the report — a customer form, an ISIR layout, a ballooned spreadsheet, or another stated template — is part of the requirement. A free-form dimensional list may be enough for some programmes and insufficient for others. Photographs can support a report; they do not replace measured values or gauge results. Language of the report, units, and the drawing revision printed on the form should match the revision that was actually measured.
What to write in the RFQ
State whether a first-article, ISIR or layout inspection is required, the revision it should follow, the characteristics or the form to be used, and whether the parts must come from the production-intent route. Include material, finish, volume and any other documents you need. Send the drawing with the request form or to anna@sunhyings.com. A wider list of enquiry items is in what to include in a made-to-print RFQ.
This article is a capability and commercial note. It is not a certificate, a dimensional data book, or evidence of customer approval. Catalogue type codes and example grades do not replace the customer’s item number, material specification or drawing revision.