Positive material identification — a spectrometric check, a spark or X-ray fluorescence test, or another named method — is used on made-to-print fasteners and components when the print or the order requires it. It is added to the inspection plan for the stage and the location that are specified. A mill certificate, even an EN 10204 3.1 certificate, is evidence of the material as issued or as processed; it may not replace a PMI check that the customer has asked for on the bar, the blank or the finished part. Material grade and ordinary certificates are already discussed in the note on Material grade and certificates on made-to-print parts.
What has to be named
A complete instruction names the method, the standard if one is cited, the elements or the grade window that will be accepted, the location of the reading, and whether the check is done on incoming material, on a coupon, or on the finished part. It should also say whether every piece, every heat, or a sample is checked. “PMI as usual” is not complete. If a particular instrument type is already required, it should be named so that the method can be planned, as other measurement methods are planned in the note on Measurement system and gauge agreement.
Coatings, oils and surface condition can influence some methods. A reading taken on a coated surface may not represent the base metal; a check that must be made on the base material needs a location or a preparation that the print or the order allows. Related finish comments are in the notes on Coatings for high-strength fasteners and hydrogen-embrittlement control and on Materials and finishes commonly specified on European gas-equipment prints.
Certificates and PMI are complementary, not automatic substitutes
Incoming identification of heats, the mill or processor certificate, and a PMI check can be required together. One does not silently replace the others. When EN 10204 3.1, PPAP or IMDS evidence is also requested, those documents are confirmed per order when required, as in the note on Documents that can be confirmed per order: EN 10204 3.1, PPAP and IMDS. IMDS or other substance data have to reflect the actual alloy and any later coating; a PMI reading does not by itself complete an IMDS submission.
If a substitution of grade is proposed, it is a written request, not a result of a convenient PMI window. Material substitution is not a shortcut and remains a customer decision on the revision or on a written concession, consistent with the broader rule in the note on Deviations, concessions and “use as is”.
Route, first article and packing
When PMI is in scope, it is planned in the route: the stage, the sampling, the marking or segregation of heats, and the reaction if a reading is outside the accepted window. First-article inspection, when required, should include the PMI method that will be used in series if the order places that check on the part, as in the note on First-article inspection on made-to-print parts. A laboratory analysis of a prototype coupon does not by itself approve a later handheld method if the detection limits or the location will change.
Lot identity has to follow the material through packing. A mixed-heat package that can no longer be tied to a certificate or a PMI record is not assumed. Packing and lot traceability are described in the note on Packing, labelling and lot traceability on made-to-print shipments.
Conflicts and volume
A print that names a grade and a PMI window that do not match, or that requires a method the coated part cannot support without damaging a finished face, is flagged. Those conflicts are resolved on the revision or in a written method, not by grinding a sealing face to obtain a spark. Volume belongs in the enquiry because 100% PMI and a heat-based check are different plans, and because some methods are not practical on every small fastener.
Heats, mixed bars and small parts
PMI is only as useful as the identity of the piece in front of the instrument. Bars, coils, headed blanks and finished parts have to remain tied to a heat or a batch. A bin that has been topped up with leftover bars of a similar size is not a single material lot. If several heats are released into one production order, the identification and any PMI sampling have to be able to tell them apart, or the heats should not be mixed.
Very small fasteners and thin washers can be awkward for some handheld methods: the reading may see the anvil, a coating, or a neighbouring piece. In those cases a coupon from the same heat, a laboratory method, or a different location should be agreed rather than forcing a meaningless spark on a finished head. The method can be practical, but it still has to be a method that identifies the specified grade.
What to send with the RFQ
Send the current drawing revision, the material specification, finish and volume, and any already required PMI method, sampling or certificate package. If readings must be taken on the finished part, or must not damage a particular face, say so. Unspecified points will be flagged before production rather than assumed.
This article is a capability and commercial note. It is not a certificate, a dimensional data book, or evidence of customer approval. Catalogue type codes and example grades do not replace the customer’s item number, material specification or drawing revision.