Packing, labelling and lot identity on a made-to-print shipment are part of the order, not an afterthought at despatch. The quantity in a bag or a carton, the labels that must appear, the way lots are kept apart, and any customer packing specification have to be stated, or the quotation will describe a proposed default and wait for agreement. A photograph of a carton on this site is not a packing specification, and it is not evidence of a standard pack that will be used on every item.

SUNHY packs automotive fasteners and gas-equipment components to the agreement for the order. If the drawing itself carries packing, cleanliness or labelling notes, those notes are production requirements, not optional comments. They belong in the RFQ together with the geometry and the finish.

Pack quantity and the unit the customer will receive

The enquiry should say whether parts are to be packed in a stated quantity, in a particular bag, box or layer arrangement, or in a customer returnable. If mixed items must never share a carton, or if kits are required, that has to be written down. “Export packing” or “safe for sea freight” is not a complete instruction. Where a preferred pack is not stated, a proposal can be offered for agreement; it is not assumed to be acceptable because it was used on another part.

Protection of threads, sealing faces and coatings — caps, separators, paper, or a named VCI — is included when it is specified. Informal extra wrapping “to be careful” is not a substitute for a cleanliness or preservation requirement that the print already states, and it is not added as an unpriced habit.

Labels, marks and what they must say

Label content follows the customer instruction: item number, revision, quantity, lot or batch, purchase-order number, and any additional text or barcode the programme uses. If a particular label layout or a plant code is already defined, attach it. A SUNHY lot mark alone is not assumed to satisfy a customer label standard.

Marks on the part itself — a head mark, a stamped item number, a bag tag tied to a serial — are a different requirement from the carton label. They are produced only as the print or the order specifies. A property class, for example, is not stamped because the parts were heat-treated; it is applied when that mark is required, as noted in the article on head styles.

Lot traceability and the documents that travel with the goods

Traceability means that a shipment can be linked to a defined lot of parts and to the records that belong to that lot: material, and, where they were agreed, heat treatment, coating and inspection. The depth of that linkage is confirmed per order. A request to “keep full traceability” should be made specific: to the heat, to the box, to the individual piece, or to another stated rule.

Material certificates such as EN 10204 3.1, inspection records, and any agreed packing list have to match the lots that are actually shipped. They are not assembled from a neighbouring lot to close a file. The note on documents that can be confirmed per order and the note on matching the material grade to the certificate apply.

Mixed revisions, mixed finishes and work in process

Parts made to two drawing revisions, or in two coating states, are not mixed in one labelled pack unless the customer writes that instruction. After a revision change, packing and identification have to follow the agreement on work in process, as described in the note on drawing revision control.

If a lot is on hold, or a concession applies to only part of a quantity, the packing and the paperwork have to keep that split visible. Silent mixing is not a way to complete a delivery.

Cleanliness, destinations and split shipments

Some programmes add a cleanliness or a particle requirement, or they forbid certain packing materials near a coating or a sealing face. Those notes, when they are on the print or in an attached packing specification, are part of the route, including any washing or handling step that they imply. A general promise of “clean packing” is not a substitute for a stated method or a limit. If no such requirement exists, one is not invented in order to decorate the quotation.

Split shipments, several unloading points, or a request to hold stock and release against call-off all affect how lots are identified and how documents travel. Those commercial arrangements are agreed in writing. They do not, by themselves, authorise mixing revisions or finishes in one labelled pack, and they do not replace the need for a packing specification. If a third-party warehouse or a customer hub will relabel the goods, the identity that leaves this site still has to match the lot records that were issued with the shipment.

What to write in the RFQ

State the pack quantity, the label content or the packing specification, the traceability rule you need, and any preservation or cleanliness note that applies, together with the current drawing revision. If a customer packing standard already exists, attach it. Send the drawing and those instructions with the request form or to anna@sunhyings.com. A wider list of enquiry items is in what to include in a made-to-print RFQ.

This article is a capability and commercial note. It is not a certificate, a dimensional data book, or evidence of customer approval. Catalogue type codes and example grades do not replace the customer’s item number, material specification or drawing revision.